Julimar Development Project Milestones
- April 2007 – Julimar-1 gas and condensate discovery
- September 2007 – Brunello-1 gas and condensate discovery
- October 2009 – Apache Corporation and KUFPEC sign agreements to join the Wheatstone LNG Project as natural gas suppliers and foundation equity partners
- May 2010 – FEED commences for the Julimar Development Project (JDP)
- November 2010 – Preliminary Development Plan (PDP) submitted to government
- December 2010 – Wheatstone Project Agreements signed
- April 2011 - JDP Environmental referral submission to DSEWPC for approval
- May 2011 - Final Field Development Plan submitted to Government
- June 2011 - Production License Application
- August 2011 - JDP Environmental Approval
- August 2011 - Formal approval of Final Field Development plan received
- August 2011 - Production License Offer received
- September 2011 - Final Investment Decision (FID)